Insights LiFePO4

How to Size a Battery Bank for a Solar Surveillance Trailer

Size a LiFePO4 battery for a solar surveillance trailer: list the loads, choose days of autonomy, pick 12, 24 or 48 V, and check winter solar and cold charging.

Mobile solar surveillance trailer with camera mast and solar panels on a construction site at dusk, with an EEMENTOR ENERGY LiFePO4 battery visible in its open equipment cabinet
Mobile solar surveillance trailer with camera mast and solar panels on a construction site at dusk, with an EEMENTOR ENERGY LiFePO4 battery visible in its open equipment cabinet

Quick answer: list every load and its hours per day, multiply by the days the trailer must run without sun, divide by the share of capacity you plan to use, then pick a battery at your system voltage that stores at least that much energy. For a typical four-camera trailer of about 1,191 Wh a day, two days of autonomy needs roughly 2,978 Wh: a 25.6 V 200 Ah LiFePO4 battery. Then check two winter limits: whether the solar array refills the battery on a short day, and whether the battery can be charged below 0 °C.

Mobile surveillance trailers watch construction sites, car parks, events and remote assets where there is no grid power. The battery decides whether the cameras still record on the third cloudy day in January. This guide walks through the sizing with a worked example; the loads and assumptions are examples, so replace them with your equipment's real figures.

Step 1: list the loads

Write down every device, its average power and how many hours a day it runs. Use measured or datasheet power, not the power supply's rating. Our example trailer:

Load Average power Hours per day Energy per day
4 IP cameras with night IR 24 W 24 h 576 Wh
Network video recorder (NVR) 15 W 24 h 360 Wh
4G/5G router 8 W 24 h 192 Wh
Floodlight on motion 40 W 1.5 h 60 Wh
Siren and strobe tests 30 W 0.1 h 3 Wh
Total about 50 W on average 1,191 Wh

The cameras, recorder and router run around the clock, so they dominate. A floodlight or a heater can change the result completely: if your trailer heats its cabinet or cameras in winter, add that load too.

Step 2: choose the days of autonomy

Autonomy is how many days the battery must carry the load with little or no solar input. Sites that rely on solar alone usually plan for two to three days; trailers with a backup generator can plan for less. Then divide by the share of the rated capacity you plan to use. LiFePO4 tolerates deep discharge well, but keeping a reserve protects against cold, ageing and the unexpected; this example plans to use 80%.

  • 1 day: 1,191 Wh × 1 ÷ 0.8 = about 1,489 Wh
  • 2 days: 1,191 Wh × 2 ÷ 0.8 = about 2,978 Wh
  • 3 days: 1,191 Wh × 3 ÷ 0.8 = about 4,466 Wh

Step 3: pick the system voltage and the battery

Use the voltage your cameras, recorder and solar charge controller are built for. For the same power, a higher voltage halves the current: the example's 50 W average is about 3.9 A at 12.8 V but 1.9 A at 25.6 V, which means thinner cables and less loss along the mast. Our standard LiFePO4 models, which can be ordered without customisation:

Bar chart: energy needed by the example surveillance trailer using 1,191 Wh a day at 80% usable capacity, 1 day 1,489 Wh, 2 days 2,978 Wh, 3 days 4,466 Wh, compared with standard LiFePO4 models: 12.8 V 100 Ah 1,280 Wh, 12.8 V 200 Ah 2,560 Wh, 25.6 V 100 Ah 2,560 Wh, 25.6 V 200 Ah 5,120 Wh, 51.2 V 100 Ah 5,120 Wh.
Example trailer (1,191 Wh a day): energy needed for 1 to 3 days of autonomy, against our standard LiFePO4 models.
Model Voltage Capacity Energy Self-heating
LFP12100-LCD 12.8 V 100 Ah 1.28 kWh Yes (LCD model)
LFP12200-LCD 12.8 V 200 Ah 2.56 kWh Yes (LCD model)
LFP24100-BL 25.6 V 100 Ah 2.56 kWh No
LFP24200-WF 25.6 V 200 Ah 5.12 kWh No
LFP48100-BL 51.2 V 100 Ah 5.12 kWh No

For the example's two days (about 2.98 kWh), the 25.6 V 200 Ah battery (5.12 kWh) fits with margin. A 12.8 V system would need more than one 200 Ah battery; ask us whether your chosen model can be connected in parallel, or consider a custom pack sized exactly to the trailer. Specifications for every model are on our surveillance trailer batteries page.

Step 4: check the solar array in winter

The solar array must refill the daily energy on the shortest days, not just in summer. A rough check divides the daily energy by the winter peak sun hours at the site and by an overall efficiency for panel angle, temperature, charge controller and battery losses. With an example 2 peak sun hours and 75% efficiency, 1,191 Wh a day needs about 794 W of panels. Peak sun hours vary widely with latitude and season: get your site's monthly figures from the EU's PVGIS tool. If the mast and trailer cannot carry enough panels for winter, plan a generator or fuel cell as backup and size the battery for the gap between runs.

Step 5: plan for cold charging

LiFePO4 should not be charged below about 0 °C unless the battery is built for it; charging a cold cell can damage it permanently. A trailer that sits outside all winter needs one of these:

  • a battery with a self-heating function, such as our 12.8 V LCD models, which warm the cells before they accept charge;
  • an insulated or heated cabinet that keeps the battery above freezing;
  • a battery management system that blocks charging below 0 °C, accepting that the solar input is lost on frozen mornings.

Our 24 V and 48 V standard models do not list a heating function, so for those voltages in cold climates we build a custom pack with heating or recommend a heated enclosure. Read lithium battery safety: storage, charging and handling for the general rules.

Step 6: monitoring and towing

Unattended trailers benefit from remote battery data. Our smart models offer Bluetooth or Wi-Fi monitoring, and the 51.2 V models add RS485 and CAN, so the trailer's controller can report state of charge and warn before the cameras go dark. The battery also has to survive towing over site roads: mount it firmly, protect the terminals and route the cables away from sharp edges. See our guide to enclosure design, IP rating and vibration.

Getting the battery

For the example above, the 25.6 V 200 Ah model can be ordered as it is from the standard models table. If your trailer needs a different voltage, a heated pack, a specific size or communication with the controller, send us the load list, the autonomy and the site's climate through our surveillance trailer batteries page, and our engineers will size it.

Frequently asked questions

How big a battery does a solar surveillance trailer need?

Add up the daily energy of every load, multiply by the days the trailer must run without sun, and divide by the share of capacity you plan to use. In our example, 1,191 Wh a day for two days at 80% usable gives about 2,978 Wh, which a 25.6 V 200 Ah battery (5,120 Wh) covers.

Should a surveillance trailer use 12 V, 24 V or 48 V?

Use the voltage your cameras, recorder and charge controller expect. For the same power, a higher voltage means lower current, thinner cables and less loss, so 24 V or 48 V suits larger trailers; 12 V suits small systems and equipment built for 12 V.

How many days of autonomy should a surveillance trailer have?

Two to three days is a common planning range for sites that rely on solar alone, because a run of cloudy winter days is when the battery has to carry the load. A trailer with a backup generator can use a smaller battery, because the generator covers the long gaps.

Can LiFePO4 batteries be charged in winter on a surveillance trailer?

LiFePO4 should not be charged below about 0 °C unless the battery is built for it. In our standard range, the 12.8 V LCD models have a self-heating function; for 24 V or 48 V with heating or an insulated, heated enclosure, ask us for a custom pack.

How much solar panel does a surveillance trailer need?

Enough to refill the daily energy on a short winter day. In our example, 1,191 Wh a day with an assumed 2 peak sun hours and 75% overall efficiency needs about 794 W of panels. Use your site's real winter solar data, for example from the EU's PVGIS tool.

Need a custom battery pack?

Design it in 3D in minutes, or send us your requirements for an engineering quote.

Design in 3D Request a quote
All articles